Design build finance and operate
An example of a design build finance and operate procurement route is a public private partnership (PPP), the most common form of which is a private finance initiative (PFI) project (ref. HM Treasury Public private partnerships).
A single contractor (perhaps a special purpose vehicle (SPV), with design, construction and facilities management expertise as well as funding capability) is appointed to design and build the project and then to operate it for a period of time. The contractor finances the project and leases it to the client for an agreed period (perhaps 30 years) after which the development reverts to the client.
As this is a very long-term relationship, entered into before any design work is undertaken, it is extremely important that the client defines their requirements very carefully, in particular the quality that is required and how it will be judged. A great deal of risk is given to the contractor, however the price they offer will reflect this.
PFI is one of the three procurement routes favoured by the Government Construction Strategy for central civil government projects.
Variations include: design build operate (DBO), and build, own, operate, transfer (BOOT).
In 2011, two government reports concluded that PFI contracts have not been a good use of taxpayers money, suggesting that PFI cost five times more than conventional government procurement. The banks, funding institutions and professions have not been prepared to take the risk associated with PFI projects, and it has instead been transferred to the building contractors and operating companies which have offered high prices in return.
The attraction to government is that PFI projects do not appear on the balance sheet, albeit piling up debt in the public sector with as much as twenty five year commitments. The recommendation of the reports is that in future PFI liabilities should be shown on treasury accounts. This may reduce this type of government contracting in the future.
For a detailed description of the sequence of activities necessary on a PFI contract see the free work plan: Public project: outline work plan.
[edit] Related articles on Designing Buildings Wiki
- Build, own, operate and transfer (BOOT).
- Design and build.
- Design and build - pros and cons.
- Design, build, finance, maintain DBFM.
- Design Build Finance Operate Maintain DBFOM.
- Design Build Finance Transfer (DBFT).
- Design build operate (DBO).
- Design Build Operate Transfer DBOT.
- Design construct manage finance DCMF.
- Government Construction Strategy.
- Infrastructure UK.
- PF2.
- Procurement route.
- Private Finance Initiative.
- Public Private Partnership.
- Public procurement.
- Renovate, operate, transfer (ROT).
[edit] External references
HM Treasury PFI / PPP guidance. 25 July 2013.
Featured articles and news
RTPI leader to become new CIOB Chief Executive Officer
Dr Victoria Hills MRTPI, FICE to take over after Caroline Gumble’s departure.
Social and affordable housing, a long term plan for delivery
The “Delivering a Decade of Renewal for Social and Affordable Housing” strategy sets out future path.
A change to adoptive architecture
Effects of global weather warming on architectural detailing, material choice and human interaction.
The proposed publicly owned and backed subsidiary of Homes England, to facilitate new homes.
How big is the problem and what can we do to mitigate the effects?
Overheating guidance and tools for building designers
A number of cool guides to help with the heat.
The UK's Modern Industrial Strategy: A 10 year plan
Previous consultation criticism, current key elements and general support with some persisting reservations.
Building Safety Regulator reforms
New roles, new staff and a new fast track service pave the way for a single construction regulator.
Architectural Technologist CPDs and Communications
CIAT CPD… and how you can do it!
Cooling centres and cool spaces
Managing extreme heat in cities by directing the public to places for heat stress relief and water sources.
Winter gardens: A brief history and warm variations
Extending the season with glass in different forms and terms.
Restoring Great Yarmouth's Winter Gardens
Transforming one of the least sustainable constructions imaginable.
Construction Skills Mission Board launch sector drive
Newly formed government and industry collaboration set strategy for recruiting an additional 100,000 construction workers a year.
New Architects Code comes into effect in September 2025
ARB Architects Code of Conduct and Practice available with ongoing consultation regarding guidance.
Welsh Skills Body (Medr) launches ambitious plan
The new skills body brings together funding and regulation of tertiary education and research for the devolved nation.
Paul Gandy FCIOB announced as next CIOB President
Former Tilbury Douglas CEO takes helm.
UK Infrastructure: A 10 Year Strategy. In brief with reactions
With the National Infrastructure and Service Transformation Authority (NISTA).
Comments